SMED - single minute exchange of die
- Details
- Written by: Super User
- Category: SMED - single minute exchange of die
- Hits: 329
Die changeover (setup) times on the production floor are an invisible area of loss for most businesses. The machine stops, operators rush about, and production waits. So what is the way to shorten this time radically? The most critical answer in the SMED (Single-Minute Exchange of Die) technique, and the one most often overlooked, is: Advance Preparation.
What Is SMED, and Why Advance Preparation?
SMED is a systematic lean production technique, developed at Toyota by the Japanese industrial engineer Shigeo Shingo, that aims to bring machine die and tool changeover times down to single-digit minutes (under 10 minutes). The successes Shingo achieved with this method delivered an average improvement of 94% in changeover times (for example, bringing 90 minutes down to under 5 minutes).
So what is the key to this striking improvement? At the root of Shingo's approach lies analyzing every step in the changeover process and making as many steps as possible doable "while the machine is running". This is where advance preparation comes in.
Read more: The Secret of Success in SMED: Advance Preparation
- Details
- Written by: Super User
- Category: SMED - single minute exchange of die
- Hits: 326
For businesses, optimizing production processes, lowering costs, and gaining a strategic competitive advantage are of critical importance. At this point SMED (Single Minute Exchange of Die), that is, die changes in single minutes, comes into play. SMED is a method that aims to minimize die-change or model-change times. In this article we will cover what SMED is, how it is done, and the advantages it provides to businesses.
What Is SMED?
SMED is a methodology developed in the 1950s by Shigeo Shingo, a Japanese engineer and business leader. This method, initially named "Single Minute Exchange of Die," aims to reduce die-change times to less than ten minutes. Today, however, the purpose of SMED is to revise the target times set for job changes and to make processes faster, more efficient, and more cost-effective.
How Is SMED Done?
Applying SMED in a business, as with every lean production technique, becomes possible when management support is secured. Along with that, applying SMED includes a series of steps:
- Details
- Written by: Super User
- Category: SMED - single minute exchange of die
- Hits: 391
Although it is a phrase spoken in very general terms, the general view of competition in the market has changed as a striking result of the "Globalization" current. It is now possible to buy any product from anywhere in the world. Moreover, thanks to Google and similar services, a company at the other end of the world can be your competitor in the place where you are, without even any knowledge of a foreign language being required. In such an environment, "Speed" comes to the fore among the elements of competition. We are not talking about fast production here. Our subject is delivery times.
Many retail chains now, besides buying in high quantities, want all of these purchases to be delivered just in time. Moreover, they usually want them within a short time. That is, they do not give you the order months in advance, as they used to, and they cannot. Because supplying the products sold in the retail store in line with customer demand is generally cheaper. No company wants to take the risk anymore of a product that may not sell.
Read more: SMED - Speed: The Fundamental Element of Competition!
- Details
- Written by: Super User
- Category: SMED - single minute exchange of die
- Hits: 300
Although I wrote the title as a 5-ton mold, the weight does not matter. In terms of changeover time, there is almost no difference between a mold weighing 250 grams and a mold weighing 30 tons. What must be done is the same.
Let us now explain, in order, what must be done to reduce the changeover time. In many production plants, mold changeover time has become a problem. For the changeover of high-tonnage molds, machines stand idle for hours, throughout shifts, and even for days. (Did these times seem long to you? Look at your own plant and see how long you are stopped.)
Not changing the mold and running very long production runs may look like an easy alternative, but it is not recommended, because it leads to carrying inventories worth millions of lira.
- Details
- Written by: Super User
- Category: SMED - single minute exchange of die
- Hits: 310
Plastic injection molding is developing rapidly in Turkey. Our companies that produce plastic parts and molds have now begun to appear at mold fairs, plastics fairs, and supplier-industry fairs. Turkish companies are increasingly gaining a say across Europe. In this article I will address mold changeover time, one of the fundamental problems of mold companies and injection-molding companies.
A duration of around 2-6 hours is considered normal for a mold changeover. Many companies have chosen to reduce the cost of this changeover time through batch-based production, and in doing so they have come to know inventory cost. The common view of engineers on this subject is to confirm that the hours stated above are correct.
Read more: Mold Changeover Time on Injection Molding Machines