Plastic injection molding is developing rapidly in Turkey. Our companies that produce plastic parts and molds have now begun to appear at mold fairs, plastics fairs, and supplier-industry fairs. Turkish companies are increasingly gaining a say across Europe. In this article I will address mold changeover time, one of the fundamental problems of mold companies and injection-molding companies.

A duration of around 2-6 hours is considered normal for a mold changeover. Many companies have chosen to reduce the cost of this changeover time through batch-based production, and in doing so they have come to know inventory cost. The common view of engineers on this subject is to confirm that the hours stated above are correct.

 

First, let us review the times involved in a mold changeover. When we examine the time spent during a mold changeover, we encounter the following;

. Mold heat-up and cool-down time

. Mold preparation time

. Possible problems on the mold

. Carrying the new mold to the machine and the outgoing mold away from the machine

. Fetching and searching for wrenches, materials, and the like

. Clamping method (clamp, quick clamping)

. Temperature-controller connections

. Hydraulic connections

. Walking around the machine

. Changes in the machine program

When you, too, carry out the same examination, you will see that much of this time is time not spent clamping and removing the mold. Most of the time is spent walking, waiting, searching, fetching, and carrying. To eliminate these, it will be enough for you to apply the following.

Eliminating walking

Eliminating walking depends on performing the operations in sequence. Because employees generally do the work in a different order every time, they often go several times to a place they need to go only once, and they spend extra time. Preventing this consists only of a procedural change. In other words, you will prevent the losses by putting the work in sequence.

Apart from this, preparation in advance saves time during the changeover. That is, you must find a way to prepare the necessary materials and equipment in advance. In this way you will not spend your valuable time on unnecessary walking during the changeover.

If possible, having more than one operator make the changes at suitable places on the machine will prevent them from walking.

Eliminating waiting

Waiting is not something everyone can see immediately. Most of the time we see employees doing something. That does not mean they are not waiting. The key point is whether they are doing the necessary work. Since their task is the model changeover, work done other than the changeover while the machine is stopped falls into the category of waiting.

Eliminating waiting is closely related to what you are waiting for. For example, if you are waiting for the mold to cool down or heat up, you need to try mounting or removing the mold without cooling it, or by heating it. If you are waiting for material to arrive, you should do advance preparation and subsequent preparation.

Eliminating searching, fetching, and carrying

Eliminating searching is related to the level of 5S. For this, you should start 5S work in your company and encourage all employees to succeed in the practices. 5S will save you a significant amount of mold changeover time.

Eliminating searching, fetching, and carrying also depends on the work related to advance preparation. Doing advance preparation and subsequent preparation will reduce fetching and carrying to a minimum.

Conclusion

The methods described here are quite simple, easy methods. With the help of these methods, however, it is possible to eliminate 75% of the 2-6 hours while spending almost nothing. The changes made here are only procedural changes. They do not require spending.