What needs to be discussed in order to set a kanban system:

  • Order distribution by model (daily, weekly, monthly, yearly)
  • The delivery time they ask for, or that you can give (the time that passes between the kanban card reaching you — the signal arriving — and your producing and delivering the required goods)
  • Pack or container quantities (the quantity that will correspond to one card)
  • Order deviations (determined in the light of the data in item 1)

What needs to be determined in the light of these data:

  • The total number of cards for each model is calculated with the help of the delivery time, which is calculated on the basis of model-change times.
  • The point at which production starts is determined.

Other points to watch:

  • A pull system also has to be set up as a basis. That is, while working with a kanban system from the end of the line, the points that feed the line must also work with kanban. Otherwise kanban does not work, and it ceases to be kanban.
  • If the total of the changeover time required each day for each model exceeds 10% of the total working time, work to reduce the model-change time should be done, or working with kanban should be given up.
  • A final tip: "While you are still inexperienced, a little stock is better than production stopping."

We use cookies

We use cookies on our website. Some of them are essential for the operation of the site, while others help us to improve this site and the user experience (tracking cookies). You can decide for yourself whether you want to allow cookies or not. Please note that if you reject them, you may not be able to use all the functionalities of the site.